By Mr. Henry — International Sales Manager at Ningbo Tianan Imp. & Exp. Co., Ltd.
Mr. Henry has 15+ years of experience in power equipment export across Asia, Africa, the Middle East, and South America, specializing in substation solutions, Power Transformers, and switchgear for utility and infrastructure projects.
Power factor correction in an industrial 33kV distribution system is not a one-size-fits-all calculation. The sizing of capacitor banks and series reactors depends on the existing load profile, the harmonic distortion background, and the target power factor specified by the utility or regulatory code. I have overseen the design and supply of power factor correction systems for over 60 Industrial Substations across three continents, and the most common engineering error I see is selecting capacitor bank kVAR based solely on uncorrected power factor without accounting for harmonic resonance conditions. This article presents the calculation method for capacitor bank and reactor sizing in 33kV systems with harmonic filtering, using the IEC 60871-1 and IEEE Std 18 frameworks that we apply in Tianan’s engineering review process.

Step 1: Establish the Target and Measured Baseline
Before any component selection begins, the system’s existing power factor must be measured at the 33kV incoming feeder over at least one full production cycle (typically 7-14 days). The measurement should capture both peak demand and light-load conditions because a fixed capacitor bank sized for peak correction will over-correct during low-load periods, causing voltage rise and potential utility penalties. The target power factor for most industrial systems is 0.95-0.98 lagging, as mandated by utility tariffs in markets such as Malaysia (TNB), Indonesia (PLN), and several Middle Eastern grid codes.
The required capacitor bank rating in kVAR is calculated using the formula:
Qc = P × (tan φ₁ − tan φ₂)
Where P is the active power demand at the 33kV bus (in kW) measured at peak, φ₁ is the angle of the uncorrected power factor, and φ₂ is the angle of the target power factor. For a typical cement plant drawing 8,000 kW at 0.78 PF (φ₁ = 38.7°) with a target of 0.96 PF (φ₂ = 16.3°), the calculation yields Qc = 8,000 × (0.802 − 0.292) = 4,080 kVAR. This is the gross capacitance requirement before harmonic and voltage considerations are applied.
Step 2: Select the Capacitor Unit Voltage: Harmonic Survey — The Overlooked Variable
Every industrial 33kV system contains harmonic currents generated by variable frequency drives (VFDs), arc furnaces, welding machines, and UPS systems. The harmonic spectrum varies by industry: a steel rolling mill may have significant 5th and 7th harmonics from DC drives, while a petrochemical plant with large VFD banks produces higher 11th and 13th harmonics. These harmonics matter because a capacitor bank and the system inductance form a series LC circuit with a natural resonance frequency. If this resonance coincides with a prominent harmonic order, the result is harmonic amplification — capacitor currents can exceed 150% of rated value, leading to fuse blowing, capacitor can rupture, and transformer overheating.
The resonant frequency of a capacitor bank connected to a 33kV bus is:
fr = f × √(Ssc / Qc)
Where f is the fundamental frequency (50 or 60 Hz), Ssc is the short-circuit capacity at the 33kV bus (in MVA), and Qc is the capacitor bank rating (in kVAR). For example, with Ssc = 600 MVA, Qc = 4,080 kVAR at 50 Hz:
fr = 50 × √(600,000 / 4,080) = 50 × 12.13 = 606 Hz
The 5th harmonic is 250 Hz, the 7th is 350 Hz, and the 11th is 550 Hz. This calculation shows the bank resonance at 606 Hz is dangerously close to the 11th harmonic (550 Hz) and 13th harmonic (650 Hz), both of which are present in many industrial systems. The solution is to add series reactors to detune the bank. Series reactors shift the resonant frequency below the lowest prominent harmonic order, typically to 189-210 Hz (3.78-4.2 pu), which places the resonance below the 5th harmonic (250 Hz) and avoids amplification of all characteristic harmonics.
Step 3: Detuned Reactor Selection and Sizing
The series reactor is expressed as a percentage of the capacitor bank impedance at fundamental frequency. Standard detuning factors are 5.67% (resonance at 210 Hz), 7% (resonance at 189 Hz), and 14% (resonance at 134 Hz). For 50 Hz systems with significant 5th harmonic content, a 7% reactor is the standard choice. The 7% reactor shifts the parallel resonance to 189 Hz (3.78 pu), safely below the 250 Hz 5th harmonic. The reactor also limits inrush current during capacitor switching from 80-120 times rated current to 15-25 times rated, protecting both the capacitor and the switching device.
The reactor rating is calculated as:
L = (p × V²) / (2πf × Qc) × 10³
Where p is the detuning factor in decimal (0.07), V is the phase-to-phase voltage (33 kV), f is frequency (50 Hz), and Qc is the capacitor bank rating (4,080 kVAR). For our example:
L = (0.07 × 33,000²) / (2π × 50 × 4,080,000) × 10³ = 5.96 mH per phase
The reactor must be rated for continuous fundamental current plus harmonic current content. IEEE Std 18 permits capacitors to operate at 135% of rated RMS current including harmonics. The reactor must match or exceed this current rating. For this 4,080 kVAR bank at 33 kV, the fundamental current per phase is 4,080 / (√3 × 33) = 71.4 A. With 135% harmonic allowance, the reactor continuous current rating should be at least 96.4 A. Capacitor cabinets with integrated reactors are our standard configuration for 33kV industrial installations.
Step 4: Capacitor Bank Configuration and Protection
For 33kV systems, the capacitor bank is typically configured in a star (wye) connection with an unbalance protection scheme. Each phase contains capacitor units connected in series-parallel to achieve the required voltage rating and kVAR. Single capacitor units rated at 7.2 kV to 12 kV are common for 33kV banks, connected in series strings of 3-5 units per phase. A 4,080 kVAR bank at 33 kV with 7.2 kV capacitor units would use four parallel units per series group, with five groups in series: 4 units × 5 groups × 3 phases × 12.5 kVAR per unit = 4,500 kVAR total (with 10% allowance for tolerances).
Protection includes: individual capacitor unit fuses (internal or external), overcurrent relay on the bank feeder, overvoltage relay (trips at 110% of rated voltage, 0.5 second delay), and unbalance current relay for the star-connected bank. The unbalance relay detects internal fuse operation or capacitor unit failure by measuring the neutral-to-ground current. A 0.5 A unbalance current threshold is typical, with a 0.1 second time delay to avoid nuisance tripping during switching transients.
For harmonic filtering applications specifically, the capacitor units must be rated for continuous harmonic current. Standard power capacitors have a 135% of rated RMS current capability, but for heavy harmonic environments (total harmonic distortion exceeding 10%), we specify capacitor units with 150% current rating at a 10-15% cost premium. The dielectric material is polypropylene film with a self-healing metallized electrode, rated for 2,000+ discharge cycles per IEC 60871-1 (IEC Standards for Power Equipment).
Step 5: Switching Device and Transient Control
Switching a capacitor bank at 33kV generates inrush current and transient overvoltage that stresses both the switchgear and the reactive components. Vacuum circuit breakers (VCBs) rated at 36 kV, 25 kA breaking capacity are standard for 33kV capacitor switching. However, back-to-back switching — when a second capacitor bank is switched while the first bank is already energized — produces inrush current that can reach 10-20 kA peak with frequencies of 2-10 kHz unless mitigation measures are applied.
The solution is either pre-insertion resistors on the VCB (reduces inrush to 3-5x rated current) or synchronized switching controllers that close the VCB contacts at the voltage zero-crossing point. Synchronized switching is the preferred method for harmonic filter banks because it also reduces the voltage transient magnitude to approximately 1.2 pu compared to 2.0-2.5 pu with random closing. The cost increment for synchronised switching is approximately $3,500-$6,000 per VCB — usually justified for filter banks above 3,000 kVAR where transient energy is significant.
Step 6: Automatic Control and Step Configuration
For industrial loads that vary throughout the day, a single fixed capacitor bank is rarely optimal. The standard approach is to split the total compensation into multiple steps, with an automatic power factor controller (APFC) switching steps in and out to maintain the target PF. For the 4,080 kVAR example, a practical configuration is 4 × 1,020 kVAR steps, controlled by an APFC with 6-stage output capability. Each step has its own contactor (or VCB for 33kV direct switching) and reactor.
The switching logic for harmonic filter banks must include a minimum off-time delay (typically 60-120 seconds) to allow capacitor units to discharge to below 50V before re-energization. The discharge resistors built into each capacitor unit achieve this within 5-10 minutes. For detuned filter steps with reactors, the discharge path includes the reactor winding resistance, which slows the discharge — the minimum off-time must be verified against the actual RC time constant of each step.
The APFC controller must have harmonic-insensitive voltage sensing inputs. Standard controllers measuring RMS voltage without harmonic filtering may register falsely high voltage readings in a distorted waveform, causing the controller to switch capacitors out prematurely. We specify APFC controllers with True RMS sensing and configurable switching hysteresis (typically 1.5-2.0% of setpoint) to avoid hunting. IEC 60076 power transformer standards also provide guidance on acceptable harmonic loading for step-up transformers feeding the APFC system.
Step 7: Site Verification and Commissioning
The commissioning of a power factor correction system should include three verification stages. First, insulation resistance testing of each capacitor unit (measured phase-to-ground, minimum 2,000 MΩ at 2.5 kV DC). Second, reactor inductance measurement on each phase (tolerance ±5% of calculated value). Third, 72-hour continuous monitoring of the corrected PF, total harmonic distortion (THD), and individual harmonics at the 33kV point of common coupling. The THD target per IEEE 519 is 8% for voltages above 161 kV, with individual harmonic limits varying by order. For 33kV systems connected to utility grids, we aim for THD below 5% at the interconnection point.
I have seen commissioning failures caused by loose busbar connections in the Capacitor Cabinet creating partial discharge at 33kV. Every bolted connection in a 33kV capacitor bank should be torqued to the manufacturer’s specification and verified with a torque wrench. The partial discharge test at 1.2 × rated voltage (39.6 kV) should show discharge levels below 10 pC per IEC 60871-1. Any reading above 50 pC requires investigation and rework before energization.
Total Cost of Ownership Considerations
The initial equipment cost for a 4,080 kVAR 33kV detuned harmonic filter bank (including capacitor units, reactors, VCB, APFC controller, enclosure, and installation materials) is approximately $85,000-$120,000 at current market prices. The annual electricity cost saving from improving power factor from 0.78 to 0.96 depends on the utility tariff structure. For a plant paying $0.08/kWh with a PF penalty of 2% of billed demand charges for each 0.01 below 0.95, the annual saving is $15,000-$25,000 on demand charges alone, plus reduced I²R losses in the transformer and distribution cables estimated at $5,000-$10,000 per year. The simple payback period is 3-6 years depending on the penalty structure and operating hours.
Beyond direct savings, the power factor correction system reduces the current drawn from the 33kV transformer by approximately 18-22%, which defers transformer replacement cost and increases the available system capacity for future load growth. A cement plant client in Vietnam that we supplied in 2023 recorded a 14°C reduction in transformer winding temperature after commissioning, which directly extends the transformer insulation life per the Arrhenius aging model (a 10°C reduction doubles insulation life expectancy).
Step 8: Environmental and Site-Specific Considerations
Every capacitor bank installation must account for the environmental conditions at the substation location. The ambient temperature range affects the capacitor unit’s rated current. Capacitors are rated for a maximum ambient temperature of 40°C per IEC 60871-1. For installations in Middle Eastern or South Asian environments where shade temperatures reach 50-55°C, the capacitor bank must be de-rated by 1.3% per degree above 40°C, meaning a 4,080 kVAR bank at 50°C ambient delivers only 3,550 kVAR effective compensation. Thermal management solutions in these conditions include forced ventilation fans with thermostat control, sunshade roofing over the capacitor enclosure, and white reflective paint on the enclosure surface (solar reflectance index > 80).
Altitude above 1,000 meters also requires de-rating — the dielectric strength of air decreases by approximately 1% per 100 meters above 1,000m. At 2,000m altitude, the capacitor unit voltage rating must be increased by approximately 10% to maintain the same dielectric margin. For a 33kV system at high altitude, this may require specifying 36kV-rated capacitor units instead of 33kV-rated units at a 15-18% cost premium. The series reactor insulation level must be similarly adjusted for high-altitude installations, with the creepage distance of the support insulators increased by the same factor.
Frequently Asked Questions
What is the difference between fixed capacitor banks and automatic PFC systems?
Why is harmonic filtering important for 33kV capacitor banks?
What detuning factor should I choose for my 33kV system?
Can I add power factor correction to an existing 33kV substation without upgrading the switchgear?
What maintenance does a 33kV capacitor bank require?
Our engineering team provides system design proposals and cost estimates for 33kV power factor correction and harmonic filtering projects. Contact us through the Tianan website with your load profile (kW demand, existing PF, harmonic spectrum if available) and we will prepare a preliminary sizing calculation within 5 business days.










